Phases Completed

Phase 1 – Fall 2025 to Spring 2026

The first phase of work includes multiple ramp closures, local access restrictions and detours in the two-mile improvement area. The speed limit will also drop to 45 MPH along I-465 and U.S. 31 in the construction zone while activity is occurring. Drivers may encounter delays during peak travel times in Indianapolis and Carmel.

Phase 1 will consist of three closures:

Phase 1 – Construction Map

Phase 1 – Detour for 106th from SB US 31

Phase 1 – Detour for EB 106th St

Phase 1 – Detour for SB Meridian St from I-465

Phase 2 – Spring 2026

This phase includes ramp and lane closures, local access restrictions, and detours. The following traffic impacts are already in place for Phase 2 construction:

  • Full-time inside shoulder closure and intermittent stoppages on I-465 eastbound and westbound from Spring Mill Road to College Avenue and Meridian Street northbound and southbound at the interchange
  • New traffic pattern at southbound U.S. 31 at the I-465 ramp and Meridian Street split
  • Southbound U.S. 31 reduced to a single lane between 106th street and the I-465 interchange

Phase 2 extended closures:

Phase 2 – Extended Closures

Phase 2 – Detour for SB Meridian St. from I-465

Phase 2 – Detour for EB 106th St.

Phase 2 – Detour for WB 106th St.